LOCATION: Coke & Sterling Counties, TX, approximately 30 miles north of San Angelo, TX
SIZE: 150 MW
COMMERCIAL OPERATIONS DATE:
PHASE 1: March 2008
PHASE 2: March 2009
UTILITY: ERCOT (Electric Reliability Council of Texas)
TURBINE EQUIPMENT: 80 Mitsubishi MHI 1000A / 29 Mitsubishi MHI 2400 2.4 MW
TRANSMISSION: 345 kV Transmission Line
INTERCONNECT: LCRA TSC
LAND: 20 landowners on 11,000 Acres.
CONTRACTOR: Wanzek Construction
DEVELOPER & MINORITY PARTNER: Cielo Wind Power
MAJORITY OWNER: Edison Mission Group (Irvine, CA)
HIGHLIGHTS:
- Goat Mountain will be Edison Mission Group’s first wind project in the ERCOT market
- Goat Mountain is Edison Mission Group’s second wind project in Texas
- Edison Mission Group and Cielo Wind Power have jointly developed this site