The project comprises of two sub-projects known as the Generation Project and the Transmission Project.
As part of the Generation Project, power generating stations will be built at Gull Island and Muskrat Falls in the Central Labrador region. The power stations will together generate 3,074MW. Transmission lines will be laid between Gull Island, Churchill Falls and Muskrat Falls.
The second sub-project involves laying of 1,100km-long ± 450 high voltage direct current (HVdc) link from Gull Island power station to Soldier’s Pond in Newfoundland’s Avalon Peninsula. The transmission project is referred to as Labrador-Island Link project and will commence years after completion of the Generation Project.
The LCP is currently undergoing environmental assessment. Construction is expected to commence in 2011 with a scheduled target opening in 2017. The project will result in the Labrador and Newfoundland’s electrical system running on 98% clean and renewable energy.
“The LCP is currently undergoing environmental assessment.”
Project details
The LCP is intended to make use of the untapped hydroelectric potential of the Churchill River to meet future electricity needs. About 65% of the potential generating capacity of the river is being utilised by the 5,428MW Churchill Falls Generating Station which was commissioned in 1971.
The project is also a major part of the strategy of Labrador and Newfoundland to reduce green house gas emissions. It claims to offset 16 megatons of carbon dioxide emissions a year.
It will be constructed in two phases. Construction of Muskrat Falls Generating Station and Labrador-Island Link project forms part of Phase I. Phase II involves construction of Gull Island Generating station and the Maritime Transmission Link between Bottom Brook in Newfoundland and Cape Breton in Nova Scotia.
Development
Nalcor Energy and Emera signed the project partnership agreement in November 2010. As per the agreement, the Muskrat Falls Generating Station will be 100% owned and operated by Nalcor Energy and the entire Transmission Line project will be owned by Nalcor Energy and Emera in the proportion of 51 and 49% respectively.
Nalcor Energy reserves the right to acquire full ownership of the Labrador-Island Link any time.
About 20% of the Muskrat Falls output will be provided to Emera for an investment of $1.2bn or 20% of the total project’s cost. Emera will also be responsible for 20% of the overall operating cost of the project over a 35-year contract period.
Emera will invest $600m on the Labrador-Island Link. In return, it will get Nalcor’s transmission rights in Nova Scotia, New Brunswick and New England. Ownership of Maritime Link will be transferred to Nalcor Energy at the end of the contract period for $1.
In addition to the above clauses, the agreement focuses on the economic development of the region by reserving jobs for the local population in Labrador.
The engineering, procurement and construction (EPC) contract for Phase I was awarded to Canada-based, SNC-Lavalin in March 2011. The contract is expected to be extended to Phase II as well.
Plant details
The Gull Island power station will have five Francis turbines and generate 2,250MW. It will provide 16.7 terawatt hours of electricity a year.The Muskrat Falls generating station will have four propeller or Kaplan turbines and generate 824MW.
Construction
The project involves large scale construction at Gull Island and Muskrat Falls.The Gull Island reservoir will be 232km-long. A concrete-faced and rock-filled dam measuring 99m-tall and 1,315m-long will be constructed at the site.
“The project involves large scale construction at Gull Island and Muskrat Falls.”
The Muskrat Falls reservoir will have a 32m-high and 432m-long dam in the north abutment of the river and another dam in the south abutment, measuring 29m-tall and 325m-long.
The interconnecting transmission lines of the Generation Project include laying of 203km-long 735kV line between Gull Island and Churchill Falls and 60km-long double-circuit 230kV line between Muskrat Falls and Gull Island. These lines will be installed to the north of the Churchill River with the support of lattice-type steel structures.
The Transmission project includes construction of a substation to convert a portion of AC power into DC in Gull Island and to reverse the DC into AC at Soldier’s Pond. It also involves laying of 407km-long and 60m-wide overhead HVdc line between Gull Island and Strait of Belle Isle, placing of three to five submarine cables in the strait of Belle Isle and 760km-long overhead HVdc cables from strait of Belle Isle to Avalon Peninsula.
Transmission Link will facilitate transportation of 800MW of power from LCP to the island while creating opportunity for future power exports. It is an important component of the province’s energy plan released by the Government of Labrador and Newfoundland in September 2007.