SIZE: 161 MW
LOCATION: Oldham County, Texas
OPERATING SINCE: 2012
UTILITY: Xcel Energy
TURBINE EQUIPMENT: 70 – Siemens 2.3 MW
TRANSMISSION: 345 kV Substation, Joint Use Switching Station
INTERCONNECT: Potter County Interchange
LAND: 35 landowners; 28,425 acres
CONTRACTOR: Wanzek Construction, Inc.
DEVELOPER: Cielo Wind Power
OWNER: EDF-RE US Development LLC
HIGHLIGHTS:
- Energy for approximately 56,000 households per year
- Energy delivered to SPP through shared transmission facilities